Friday, September 29, 2006

GH3.0 Update

The brick was delivered late last week; here are some quick pics. This week the builders smoothed out the base dirt in the forms and have started to lay the drains and water lines prior to pouring the concrete slab. Pics of that are to follow!

2 comments:

Todd said...

umm...don't you need walls before you need brick? Are they doing things out of order on purpose?
Hehe...at least progress is being made...

Joshua said...

I guess you can expect the appliances any day now huh? j/k :)

It is early for the brick, but if they started your house when they said they would have then it would be about the right time for brick. It appears that ACME is the only one keeping to schedule.